Husein, Saddam (2011) Tinjauan Keserasian Alat Gali Muat Angkut Untuk Mencapai Target Produksi 86.000 BCM/bulan pada Pit 3 PT. Leban Mutiara Hitam di Desa Leban Kecamatan Rantau Pandan Kabupaten Bungo Provinsi Jamb. Diploma/Proyek Akhir thesis, Universitas Negeri Padang.
![B1_SADAM HUSEIN_03407_2011.pdf.pdf [thumbnail of B1_SADAM HUSEIN_03407_2011.pdf.pdf]](https://repository.unp.ac.id/style/images/fileicons/text.png)
B1_SADAM HUSEIN_03407_2011.pdf.pdf
Download (2MB)
Abstract
PT. Leban Mutiara Hitam in early establishment named CV. Citra Perdana
and has been established since 15th September 2006, in early February 2007
changed to PT. Leban Mutiara Hitam engaged in coal mining, which has reserves
of coal sufficient potensial for development with total area of approximately 50
hectares located in the village of Rantau Pandan district Leban Muaro Bungo
District in Jambi Province.
In pit 3, PT. Leban Mutiara Hitam using the open pit system. In mining,
PT Leban Mutiara Hitam combines work as an excavator and dump trucks
unloading equipment and conveyances. Mining activities conducted include
processes: excavation, loading, transportation and land use coal excavator.
Production targets to be achieved largely determined by the productivity of this
tool work. In pit 3, the production target of 86 000 BCM of overburden / month.
In mining the role and availability of heavy equipment very important,
because with the use of heavy equipment to facilitate mining operations. In the
mining process, the planning needs of heavy equipment in mining very influential.
If the utilization of heavy equipment is not in accordance with the needs on the
ground, it can hamper the process of mining, such as queues conveyances which
resulted in waiting times at loading tool. It can be anticipated based on the value
of match factor, with the following provisions:
-MF < 1 means there waiting time in unloading equipment while working a
maximum of conveyance.
-MF = 1 means the performance of conveyance and equipment load balanced.
-MF > 1 means the waiting time occurred in transportation equipment while
unloading equipment working optimally.
At PT. Leban Mutiara Hitam problem that occurs is un balanced between the
number of tool fits with the means of conveyance that resulted in the waiting time in
unloading the tool, while the maximum conveyance work
Item Type: | Thesis (Diploma/Proyek Akhir) |
---|---|
Subjects: | T Technology > TN Mining engineering. Metallurgy |
Depositing User: | Dina Aulia Sari S.IP |
Date Deposited: | 04 Mar 2025 01:38 |
Last Modified: | 04 Mar 2025 01:38 |
URI: | https://repository.unp.ac.id/id/eprint/2980 |